Mango Hill

New state high school in Mango Hill

Project update

  • A construction contract for the new school was awarded to FK Gardner & Sons (FKG) in March 2019.
  • Roof sheeting is complete on the administration building and information services centre and the roof is installed on the central covered lunch area and canteen.
  • Partition walls are also being installed for the administration building and information services centre.
  • The science centre is well underway with columns and blockwork complete on level 1.
  • Structural works have commenced on the sports centre and will be completed shortly to allow the ground slab to be poured.

Register for new school updates.

Download images (ZIP, 141MB)