New state high school in Calliope

Project update

  • A contract for the design and construction of the new school was awarded to Paynters construction in late 2018. View the fly over footage of the works so far.
  • Painting is underway for the administration building and resource centre.
  • Wall framing is underway for the junior learning and ICT building and wall linings and building services are in progress for the science centre and junior applied technology building.
  • Internal and external cladding is being installed on the canteen and multipurpose hall.
  • Additional site works including covered links, solar power, car parking and a drop-off/pick-up zone are well underway.

Register for new school updates.