- A new state primary school in the growing area of Palmview will open for Prep to Year 6 students for 2021.
- The school is located on Peter Crosby Way at Sippy Downs and is co-located with the new special school opening for 2021.
- Mr Andrew Walker was appointed as the Foundation Principal of the new school in April 2020.
- Visit the school
Facebook page or
website.
- FK Gardner and Sons was appointed as the building contractor in early 2020 to construct the new school.
- Construction of the school commenced in early 2020.
Project update
- The administration building was handed over to the school for occupation in early November 2020.
- The prep learning centre is progressing well, with the final paint recently completed.
- External cladding works are complete for the junior learning centre.
- Construction of the multipurpose hall is progressing well, with the gym flooring system, including line marking, complete.
- The installation of wall frames and trusses have been completed for the information services centre.
- Service rough ins are progressing well for the senior learning and information services centre areas.